Cambridge News

Another year to wait for completion of new Waterbeach Station

- By HANNAH BROWN Local democracy reporter hannah.brown@reachplc.com @HannahBrow­n901

THE expected date for when work on the new Waterbeach Station will be completed has been pushed back a year.

The Greater Cambridge Partnershi­p (GCP) is now forecastin­g that the new railway station will be completed in 2026, rather than in 2025 as had originally been hoped for.

The new station will replace the existing Waterbeach Station and is required to be built before thousands of new homes can be built as part of Waterbeach New Town.

Last month the GCP said the work to complete the full business case for the project had been delayed after the rail industry had asked for additional survey work to be undertaken.

At the time the Partnershi­p said it still expected the project to be completed in 2025 despite the delay. However, a report presented to the GCP joint assembly meeting this week (February 15) said the forecast completion date for the new railway station is now 2026.

The report said the GCP is aiming to submit a full design package to Network Rail by the end of this month.

The GCP agreed to take on the project to relocate Waterbeach Station in June 2022. At the time the Partnershi­p said the scheme was expected to cost £37million to complete, but accepted there was a risk these costs could increase.

Building the new railway station was a condition of South Cambridges­hire District Council’s approval of plans to build 4,500 new homes as part of the Waterbeach New Town developmen­t.

The relocation project had been expected to be led and funded by developers, however the GCP was told in 2022 that this was no longer consid

■January, 2021 - South Cambridges­hire District Council approves outline permission for 4,500 homes as part of the Waterbeach New Town. One of the conditions is the requiremen­t for a new railway station to be built.

■ June 9, 2022 - GCP announces plans to take on the relocation project, but concerns are raised over the financial risk.

■ June 30, 2022 - GCP executive board agrees to take on the project.

■ February 2023 - ‘Work begins’ on the station as 83 markers are placed in the ground to start work ahead of the planning permission expiring.

■ January 2024 - GCP announces delays to planning work, but still forecasts 2025 completion.

■ February 2024 - GCP pushes back the forecast completion of the new railway station to 2026.

ered to be viable. The GCP agreed to take on the project in order to “unlock” the Waterbeach New Town housing, and the developer RLW Estates proposed to contribute £17million towards the cost of relocating the station.

Newspapers in English

Newspapers from United Kingdom